This article describes how to obtain output of a one-time schedule pre-expiration log.

 

Scope

 

FortiGate.

Solution


Configure a one-time schedule in FortiGate as shown below:

 
Usually the pre-expiration logs will be generated on the date the one-time schedule ends at 00:00.
In order to generate these logs, set the date/time in FortiGate to 06/01/2021 at 11:58:00 PM with an allowance of 2 minutes before 00:00:00.
 
To check pre-expiration logs generated by FortiGate, go to Log & Report -> System Events.
 

 

An automation stitch can also be configured to send an email alert for this type of event: see Technical Tip: Creating automation stitches.

 

The image below shows the trigger condition for this event.

 

Trigger_Event_One_Time_Schedule_Expiring.png