FS-424D → FS-424E Core Replacement (FortiLink + MC-LAG) – Migration Sequence
Hello TAC,
We are replacing 2 × FS-424D core switches (FortiLink-managed, configured as an MC-LAG pair with ICL) with 2 × FS-424E.
When we attempted to replace the first switch, all downstream switches and APs went offline.
Can you confirm the correct replacement sequence for this scenario, and whether the new 424E switches must be pre-configured before connection or if they will automatically inherit configuration from FortiLink after joining the fabric?