Technical Tip: How to configure scheduled report in FortiMail
Description
This article describes how to configure schedule report in FortiMail and how to verify whether the report is delivered from FortiMail.
Solution
Go to: Log & Report -> Report Settings -> Create a new report
Below is an example for last 7 days report.


This article describes how to configure schedule report in FortiMail and how to verify whether the report is delivered from FortiMail.
Solution
Go to: Log & Report -> Report Settings -> Create a new report
Below is an example for last 7 days report.


Go to: Monitor -> Log -> Mail eventThe log below will show up (stat=sent) which indicated the report is sent to userB@shathish.org via email successfully.Result: